Projects List


1. Kansai Nerolac Paints Ltd
Location: Hosur (Tamil Nadu)
Plant : Water Based Paint Plant
Year of Execution : 2018
Particulars of Work : Replacement of existing Siemens DCS with Schneider Electric Plantstruxure PES Distributed Control system
Plant : SAP Integration with Water Based Control System
Year of Execution : 2011
Particulars of Work : SAP Integration and SUPERBatch& Historian for Batch Process Management.
Location: Jainpur (U.P.)
Plant : Water Based Paint Plant
Year of Execution : 2017
Particulars of Work : IT & OT linking with Wonderware MES (Manufacturing Execution System)
Year of Execution : 2011 & 2017
Particulars of Work : Plantstruxure Distributed control system,SUPERBatch& Historian for Batch Process Management,Intelligent MCC & VFD Communication,InstrumentSupply,Installation& Calibration works.
Plant : Emulsion Plant
Year of Execution : 2013
Particulars of Work : Plantstruxure PES Distributed control system, SUPERBatch& Historian for Batch Process Management,Intelligent MCC & VFD Communication with Control system, Complete Field Instruments and Erection materials Supply,Installation& Calibration
Plant : Solvent Charging in Plant
Year of Execution : 2014
Particulars of Work : Turnkey Automation with Control System, Complete Field Instrument supply Installation & Calibration.
Location: Saykha (Gujarat)
Plant : Industrial Paint Plant
Year of Execution : 2018
Particulars of Work : Turnkey Automation with Plantstruxure PES Distributed Control System, Historian, Intelligent MCC & VFD Communication with Control system, Complete Field Instrument supply Installation & Calibration.
Location : Lote (Maharashtra)
Plant : Water Based Paints
Year of Execution : 2011
Particulars of Work : SAP Integration, SUPERBatch and Historian for Batch Process Management.
Year of Execution : 2008
Particulars of Work : PLC/SCADA Based system for Automation of TSDs,Mixers and Pigging System for Water Based Paints.
2. Asian Paints Limited
Location: Vizag (Andhra Pradesh)
Plant : Paint Plant
Year of Execution : 2019
Particulars of Work : Instrumentation Installation Work with supply of Erection Hardware
Location: Mysuru (Karnataka)
Plant : Paint Plant
Year of Execution : 2019
Particulars of Work : Instrumentation Installation Work with supply of Erection Hardware
Location: Rohtak(Haryana)
Plant : Paint Plant
Year of Execution : 2017
Particulars of Work : Instrumentation Installation Work with supply of Erection Hardware
Location: Kasna (U.P.)
Plant : Paint Plant
Year of Execution : 2016
Particulars of Work : Instrumentation Installation Work with supply of Erection Hardware
Location : Ankleshwar (Gujarat)
Plant : Industrial Paints
Year of Execution : 2013
Particulars of Work : PLC/SCADA Based system for AMC Capex and Pilot Plant Expansion.
Year of Execution : 2008
Particulars of Work : PLC/SCADA Based system for Automation of TSDs and Mixers for Water Based Paints,SUPERBatch for Batch Process Management.
Year of Execution : 1996
Particulars of Work : Turnkey Automation of 6 Alkyd Resin Reactors,DataAcquisition,Control,Recipe Management,MIS Reports.
Location : Khandala (Maharashtra)
Plant : Paints
Year of Execution : 2013
Particulars of Work : Instrumentation and Erection Installation & Calibration works with supply of material
Patancheru (Andhra Pradesh)
Location : Patancheru (Andhra Pradesh)
Plant : Industrial Paints
Year of Execution : 2003
Particulars of Work : Instrumentation works including supply of PLC based System,Installation& Erection Material.
Year of Execution : 2001
Particulars of Work : Turnkey Automation with TPMX 67 PLC & FIX 32 SCADA,Supply of Instruments,ErectionMaterial,Installation,Calibration& Commissioning.
Year of Execution : 1997
Particulars of Work : Instrumentation works including supply of PLC based System,Installation& Erection Material.
3. Berger Paints India Limited
Location: Jejuri Plant: phase-II Expansion Project
Year of execution: 2019
Particulars of Work: Turnkey Automation with Plantstruxure PES Distributed Control System, InBatch& Historian for Batch Process Management, Complete Field Instrument supply Installation & Calibration
Location: Goa Plant : Resin Plant
Year of Execution : 2019
Particulars of Work : Replacement of existing ABB DCS with Schneider Electric Plantstruxure PES Distributed Control System
4. JSW Paints Limited
Location: Vijaynagar
Plant: Water Based Paint Plant
Year of execution: 2020
Particulars of Work: Plantstruxure PES Distributed Control System with InBatch& Historian for Batch Process Management and connectivity with ERP
Location: Vasind
Plant: Industrial Paint Plant
Year of execution: 2020
Particulars of Work: Plantstruxure PES Distributed Control System with InBatch& Historian for Batch Process Management and connectivity with ERP
5. Asian PPG Industries Ltd
Location : Khandala, Maharashtra
Plant : Food Grade Paint Plant
Year of Execution : 2017
Particulars of Work : PLC/SCADA system with Supply, Installation, Erection and Commissioning for Instrumentation. Turnkey Instrumentation Work.
Location : Moraiya, Ahmedabad
Plant : Paint Plant
Year of Execution : 2016
Particulars of Work : PLC/SCADA system with Supply, Installation, Erection and Commissioning for Instrumentation. Turnkey Instrumentation Work.
Location : Sriperumbudur,Tamilnadu
Plant : Intermediate project
Year of Execution : 2011
Particulars of Work : Supply of Control systems.
Plant : Automative Paints
Year of Execution : 2008
Particulars of Work : PLC/SCADA Based system for Automation of 22 Mixers and 8 weighing station for Automotive Paint Plant
6. UK Paints India Pvt. Limited
Location: Sikandarabad,U.P.
Plant: Emulsion Resin Plant
Year of execution: 2019
Particulars of Work: Turnkey Automation with Plantstruxure PES Distributed Control System, SUPERBatch for Batch Process Management, Complete Field Instrument supply Installation & Calibration
7. AkzoNobel India Ltd
Location : Navi Mumbai
Plant : Coating Plant
Year of Execution : 2013
Particulars of Work : Supply of ESD System & Instruments.
Location : Hyderabad
Plant : Industrial Paints
Year of Execution : 2011
Particulars of Work : Instrumentation Works with Supply of Material.
8. BASF Coatings India. Ltd.
Location : Mangalore,Karnataka
Plant : Industrial Paints
Year of Execution : 2009
Particulars of Work : PLC/SCADA Based system for Automation of coatings Blenders.
9. Asian Paints Middle East LLC, Oman
Plant : Paint Plant
Year of Execution : 2016, 2017, 2018
Particulars of Work : PLC/SCADA Based system for Automation with Instrumentation and Intelligent MCC.
10. Berger Paints LLC, UAE
Plant : Paint Plant
Year of Execution : 2017, 2018, 2019
Particulars of Work : PLC Based system for Automation with Instrumentation
11. Causeway Paints Lanka (Pvt) Ltd.
Location: Sri Lanka
Plant: Paint Plant
Year of execution: 2020
Particulars of Work: Turnkey Automation with Process Control System, Complete Field Instrument supply and commissioning
12. Axalta Coating System India Pvt. Ltd.
Location: Baroda
Plant: Paint
Year of execution: 2017 & 2018
Particulars of Work: Electrical / Instrumentation Installation Work with supply of Erection Hardware


1. Fine Organics Industries Pvt. Ltd
Location : Ambernath, Maharashtra
Plant : Plant N42 Automation
Year of Execution : 2019
Particulars of Work : Plantstruxure Distributed control system for Automation of Solid plant, Instrument Installation & Calibration works with supply of material.
Plant : Phase I Automation
Year of Execution : 2014
Particulars of Work : Plantstruxure Distributed control system for Automation of Solid plant with advanced buses like profibus,SUPERBatch for Batch Process Management,Instrument Installation & Calibration works with supply of material.
Plant : Phase II Expansion
Year of Execution : 2014
Particulars of Work : Services related to control system and application software development..
Plant : Speciality Chemicals
Year of Execution : 2012
Particulars of Work : Plantstruxure Distributed control system for Automation of Solid plant Phase II Line 3 with advanced buses like profibus,SUPERBatch for Batch Process Management,Instrument Installation & Calibration works with supply of material.
2. Clean Science and Technology Pvt. Ltd
Location: Kurkumbh
Plant: Automation P7 Distillation and Batch Column plant
Year of execution: 2020
Particulars of Work: Turnkey Automation with Process Control System with Complete Field Instrument supply, Installation & Calibration.
Plant: Automation DCC Distillation and Batch Column Plant
Year of execution: 2019
Particulars of Work: Turnkey Automation with Plantstruxure PES Distributed Control System with Complete Field Instrument supply, Installation & Calibration.
Plant: Unit II
Year of execution: 2019
Particulars of Work: Energy Management System
Plant: Automation P10 Distillation and Batch Column plant
Year of execution: 2018
Particulars of Work: Turnkey Automation with Process Control System with Complete Field Instrument supply, Installation & Calibration.
Plant: Automation P8 Distillation and Batch Column Plant
Year of execution: 2018
Particulars of Work: Turnkey Automation with Process Control System with Complete Field Instrument supply, Installation & Calibration.
3. Dyna Glycols Pvt. Ltd.
Location: Gandhidham
Plant: SIL 3 Safety Control System for EO Plant
Year of execution: 2019
Particulars of Work: Turnkey Automation with M580 SIL3 Safety System with Complete Field Instrument supply, Installation & Calibration
Plant: EO Plant
Year of execution: 2008 to 2018
Particulars of Work: Turnkey Automation with Plantstruxure PES Distributed Control System with Complete Field Instrument supply, Installation & Calibration.
4. Esteem Industries Pvt Ltd
Location : Wada,Maharashtra
Plant : EO Plant Expansion
Year of Execution : 2013
Particulars of Work : PLC/SCADA based system. Installation and Calibration work with supply of material.
Plant : Speciality Chemicals
Year of Execution : 2011
Particulars of Work : Plantstruxure Distributed control system,SUPERBatch& Historian for Batch Process Management,Field Instrument Supply Installation & Calibration.
5. Fosroc Chemicals Limited
Location: Rajasthan
Year of execution: 2019
Particulars of Work: Turnkey Automation with Process Control System with Complete Field Instrument supply, Installation & Calibration.
6. Viswaat Chemicals Ltd
Location : Ambernath,Maharashtra
Plant : Automation of EO plant-1
Year of Execution : 2016
Particulars of Work : Plantstruxure Distributed control system with SUPERBatch for Batch Process Management,Instrument Installation & Calibration works with supply of material.
Plant : ECH Plant
Year of Execution : 2012
Particulars of Work : Plantstruxure Distributed control system with advanced buses likeProfibus,SUPERBatch for Batch Process Management,Instrument Installation & Calibration
7. BASF India Ltd
Location : Manglore
Plant : Black Powder Plant
Year of Execution : 2013
Particulars of Work : PLC/SCADA based system, Field Instruments and Erection materials supply, Installation and Calibration
Location : Turbhe, Navi Mumbai
Plant : 25kL Blender and pre polymer Plant
Year of Execution : 2010
Particulars of Work : PLC/SCADA based system Instrument Installation and Calibration work with supply of material
8. Tristar Intermediates Ltd.
Location: Sarigam, Gujarat
Plant: EO Plant
Year of execution: 2019
Particulars of Work: Turnkey Automation with Plantstruxure PES Distributed Control System and Batch Software with Complete Field Instrument supply, Installation & Calibration.
9. Indoamines
Location: Baroda, Gujarat
Plant: EO Plant
Year of execution: 2012 to 2019
Particulars of Work: Turnkey Automation with PLC/SCADA Control System and Batch Software with Complete Field Instrument supply, Installation & Calibration.
10. Huntsman International India
Location : Panoli, Gujarat
Plant : EO Plant
Year of Execution: 2004 to 2016
Particulars of Work : PLC/SCADA based system, Field Instruments and Erection materials supply, Installation and Calibration
Location : Baroda, Gujarat
Plant : Pigment Plant
Year of Execution: 2012 to 2016
Particulars of Work : PLC/SCADA based system, Field Instruments and Erection materials supply, Installation and Calibration
11. Veeral Additives Pvt.Ltd.
Location: Mahad – Maharashtra
Year of execution: 2020
Particulars of Work: Instrumentation Installation Work with supply of Erection Hardware
12. Dai IchiKarkkaria Ltd.
Location: Dahej
Year of execution: 2018
Particulars of Work: Instrumentation Installation Work with supply of Erection Hardware
13. PI Industries
Location: Jambussar, Gujarat
Year of execution: 2016
Particulars of Work: Instrumentation Installation Work with supply of Erection Hardwareworks with supply of material.
14. Inventys Research Company
Location : Nagpur,Maharashtra
Plant : Speciality Chemicals
Year of Execution : 2011
Particulars of Work : Plantstruxure Distributed control system for Automation, SUPERBatch& Historian for Batch Process Management
15. Tytan Organics Ltd
Location : Turbhe,Maharashtra
Plant : Speciality Chemicals
Year of Execution : 2008
Particulars of Work : PLC/SCADA Based system for Automation of Blending,Spray Drying & Powder Coating,Tank farm & MCC Automation Control & Data Acquisition System with Batch Process Management Software”SUPERBatch”.
16. Tytan Organic Chemicals FZE
Location : Sharjah
Plant : 20kL NCO Plant
Year of Execution : 2008
Particulars of Work : Open architecture based hybrid control system for 3 Nos Batch Reactors. Pneumatic valves on Asi bus, MCC I/O’s on Advantys STB remote I/O and VFD communication on “CAN Open” Bus and with Batch process management software “SUPERBatch”.
Plant : Speciality Chemicals
Year of Execution : 2004
Particulars of Work : PLC/SCADA Based System for Automation of 4 Nos. speciality Chemical reactors,Data acquisition, Control,RecipeManagement,MIS Reports.
17. Unitop Chemicals Pvt Ltd
Location : Patalganga,Maharashtra
Plant : EO Based Surfactants
Year of Execution : 2002
Particulars of Work : PLC/ SCADA based system for Automation of 2 No. Ethylene Oxide Reactor Batch Process Operation, MIS Reports.
18. Name of Company :BASF India Ltd
Location : Manglore
Plant : Black Powder Plant
Year of Execution : 2013
Particulars of Work : PLC/SCADA based system, Field Instruments and Erection materials supply, Installation and Calibration
Location : Turbhe, Navi Mumbai
Plant : 25kL Blender and pre polymer Plant
Year of Execution : 2010
Particulars of Work : PLC/SCADA based system Instrument Installation and Calibration work with supply of material
Plant : Styropor Plant
Year of Execution : 2008
Particulars of Work : Instrumentation and Electrical installation work with supply of material
19. Sequent Scientific Ltd
Location : Panoli,Gujarat
Plant : Speciality Chemicals
Year of Execution : 2011
Particulars of Work : Instrumentation work including supply of PLC based System, Installation & erection Material.
Location : Mangalore, Karnataka
Plant : Speciality Chemicals
Year of Execution : 2012
Particulars of Work : Instrumentation work including supply of PLC based System, Installation & erection Material.
20. Lanxess India Pvt. Ltd.
Location : Bharuch, Gujarat
Plant : Process & Utility Plant
Year of Execution : 2010
Particulars of Work : Instrumentation Installation & Calibration work with supply of material.
21. Sudarshan Chemical Industries
Location : Mahad,Maharashtra
Plant : Pigments
Year of Execution : 2002
Particulars of Work : PLC/ XBT Based System for Filter Press Automation and Mica Plant Automation
22. Gujarat Alkali & Chemicals Ltd
Location : Dahej, Gujarat
Plant : Hydrogen Peroxide
Year of Execution : 2010
Particulars of Work : Instrumentation Installation & Calibration work with supply of material.
23. VVF Ltd.
Location : Taloja, Maharashtra
Plant : Fatty acids
Year of Execution : 2005
Particulars of Work : Instrumentation Installation & Calibration work with supply of material.
24. Standard Alkali Ltd
Location : Navi Mumbai
Plant : Caustic Chlorine Plant
Year of Execution : 2005
Particulars of Work : Instrumentation Installation & Calibration work with supply of material.
25. Deepak Fertilizers Ltd
Location : Taloja, Maharashtra
Plant : Fertilizers
Year of Execution : 2017
Particulars of Work : Instrumentation Installation & Calibration work with supply of material
Plant : Energy Monitoring
Year of Execution : 2010
Particulars of Work : PLC/SCADA based system for Energy Monitoring.
Plant : WNA Plant
Year of Execution : 2010
Particulars of Work : Instrumentation Installation & Calibration work with supply of material.
Plant : IPA Plant
Year of Execution : 2006
Particulars of Work : Instrumentation Installation & Calibration work with supply of material.
Plant : Fertilizers
Year of Execution : 2000
Particulars of Work : Instrumentation Installation & Calibration work with supply of material.
26. Mangalore Chemicals & Fertilisers Ltd
Location : Mangalore
Plant : Agrochemicals
Year of Execution : 2014
Particulars of Work : Instrumentation Installation & Calibration work with supply of material.
Plant : Agrochemicals
Year of Execution : 2002
Particulars of Work : Instrumentation Installation & Calibration work with supply of material.


1. Kansai Nerolac Paints Ltd
Location: Saykha
Plant : CED F2 Plant
Year of Execution : 2019
Particulars of Work : Turnkey Automation with Plantstruxure PES Distributed Control System, Historian, Complete Field Instrument supply Installation & Calibration
Plant : Resin Plant
Year of Execution : 2019
Particulars of Work : Turnkey Automation with Plantstruxure PES Distributed Control System, Historian, Complete Field Instrument supply Installation & Calibration
Location: Lote
Plant : Water Based Paint Plant
Year of Execution : 2018
Particulars of Work : Turnkey Automation with Control System, SUPERBatch& Historian for Batch Process Management, VFD Communication with Control system, Complete Field Instrument supply Installation & Calibration.
Location :Hosur
Plant : Emulsion Resin Plant
Year of Execution : 2017
Particulars of Work : Plantstruxure Distributed control system, MCC & VFD Communication with Control system, Installation & Calibration.
Location :Jainpur
Plant : Emulsion Resins
Year of Execution : 2014
Particulars of Work : Plantstruxure DCS system with Supply, Installation, Erection and Commissioning for Electrical and Instrumentation.
Location : Bawal
Plant : Acrylic Plant Expansion
Year of Execution : 2011
Particulars of Work : Plantstruxure Distributed control system, SUPERBatch& Historian for Batch Process Management.Intelligent MCC & VFD Communication with Control system, Complete Field Instrument supply Installation & Calibration.
Plant : CED Resins
Year of Execution : 2009
Particulars of Work : PLC/SCADA Based system for Automation of Seven Reactors,Tank farm & MCC Automation Control & Data Acquisition System.
Plant : Acrylic Resins,AlkydResins,MF Resins
Year of Execution : 2008
Particulars of Work : Turnkey Automation with PLC/SCADA based Control System; SuperBatch Batch Management System; Calibration and Installation with supply of Material
Plant : Pilot Plant
Year of Execution : 2007
Particulars of Work : Turnkey Instrumentation work
2. Berger Paints India Limited
Location: Jejuri
Plant: phase-II Expansion Project
Year of execution: 2019
Particulars of Work: Turnkey Automation with Plantstruxure PES Distributed Control System, InBatch& Historian for Batch Process Management, Complete Field Instrument Supply Installation & Calibration
Location: Goa
Plant : Resin Plant
Year of Execution : 2019
Particulars of Work : Replacement of existing ABB DCS with Schneider Electric Plantstruxure PES Distributed Control System
Location: Anand
Plant : Emulsion Resin Plant
Year of Execution : 2019
Particulars of Work : Replacement of existing Honeywell DCS with Schneider Electric Plantstruxure PES Distributed Control System
3. IVP Limited
Plant : PU Resin Plant
Year of Execution : 2018
Particulars of Work : Turnkey Automation with Plantstruxure PES Distributed Control System, SUPERBatch& Historian for Batch Process Management, Complete Field Instrument supply Installation & Calibration
Plant : Resin Plant
Year of Execution : 2017
Particulars of Work : Turnkey Automation with Plantstruxure PES Distributed Control System, SUPERBatch& Historian for Batch Process Management, Complete Field Instrument supply Installation & Calibration and Electrical Installation.
Location : Tarapur
Plant : Coating and MDI Plant
Year of Execution : 2017
Particulars of Work : Plantstruxure DCS system with Supply, Installation, Erection and Commissioning for Electrical and Instrumentation. Turnkey Instrumentation and Electrical Work.
4.PidiliteIndusries Limited
Location: Sri Lanka
Plant : Adhesive Plant
Year of Execution : 2019
Particulars of Work : Process Control System with Supply and Commissioning
Location: Dahej
Plant : Adhesive Plant
Year of Execution : 2018
Particulars of Work : PlantStruxure PES Distributed Control System with Supply and Commissioning
Location: Vapi
Plant : Adhesive Plant
Year of Execution : 2018
Particulars of Work : Process Control System with Supply and Commissioning
Location: Jammu
Plant : Adhesive Plant
Year of Execution : 2017
Particulars of Work : Process Control System with Supply and Commissioning
Location: Vasai
Plant : Adhesive Plant
Year of Execution : 2014
Particulars of Work : Process Control System with Supply and Commissioning
5. Asian Paints Limited
Location: Bhandup (Mumbai)
Plant : CED Resins
Year of Execution : 2012
Particulars of Work : Plantstruxure Distributed control system for Automation of Solid plant with advanced buses like profibus, SUPERBatch for Batch Process Management. Instrument Installation & Calibration work with supply of material.
Year of Execution : 2011
Particulars of Work : Turnkey Automation with PLC/SCADA based Control System and SuperBatch Batch Management System.
Plant : Pilot Plant
Year of Execution : 2006
Particulars of Work : Automation of Alkyd/Emulsion Pilot plant with Utility management system,VFD Communication on “CANOPEN” Bus, & with Batch Process management Software” SUPERBatch”.
Location: Ankleshwar (Gujarat)
Plant : Emulsion Resins,Amino Resins
Year of Execution : 2001
Particulars of Work : PLC/SCADA based Control and Monitoring System for Monomer Tank farm Loading and Batching operations.
Year of Execution : 1997
Particulars of Work : Turnkey Automation with PLC/SCADA based Control System and SuperBatch Batch Management System
Plant : Alkyd Resins
Year of Execution : 1996
Particulars of Work : Turnkey Automation with PLC/SCADA based Control System and SuperBatch Batch Management System
Location: Patancheru (Andhra Pradesh)
Plant : Alkyd Resins
Year of Execution : 2001
Particulars of Work : PLC/SCADA based control and Monitoring system for Monomour tank farm loading and batching operation.
Year of Execution : 1998
Particulars of Work : Turnkey Automation of 5 Emulsion, Acrylic and Amino Resin Reactors,Data Acquisition, Control, Recipe Management,MIS Reports.
Plant : Alkyd Resins
Year of Execution : 1996
Particulars of Work : Turnkey Automation of 6 Alkyd Resin Reactors,Data Acquisition, Control, Recipe Management,MIS Reports
6. BASF Coatings India Ltd
Location : Turbhe (Mumbai)
Plant : Polyurethanes
Year of Execution : 2008
Particulars of Work : PLC / SCADA Based System,Instrument Installation & Calibration work with supply of material.
Location : Mangalore
Plant : CED Resins
Year of Execution : 2006
Particulars of Work : PLC / SCADA Based System,Dataacquisition,Control,RecipeManagement,MIS Reports.
7. Polychem Resins Ltd
Location : Dubai
Plant : Resin Plant Expansion
Year of Execution : 2015
Particulars of Work : Plantstruxure Distributed control system with SUPERBatch for Batch Process Management. Instrument Installation & Calibration work with supply of material.
Plant : Alkyd Resins, Polyester Resins
Year of Execution : 2003
Particulars of Work : Turnkey Automation of 2 Alkyd & Polyester Resin Reactors,DataAcquisition,Control, Recipe Management,MIS Reports.
8. Pouya Resins Ltd.
Location : Shiraz (Iran)
Plant : Acrylic Resins, Polyamide Resins
Year of Execution : 2002
Particulars of Work : Turnkey Automation of Acrylic and Polyamide Resin Reactors,DataAcquisition,Control,RecipeManagement,MIS Reports.
9. Cray Valley Resins Ltd.
Location : Navi Mumbai
Plant : Acrylic Resins, Polyamide Resins
Year of Execution : 2006
Particulars of Work : Turnkey Automation of Acrylic and Polyamide Resin Reactors,DataAcquisition,Control,RecipeManagement,MIS Reports.
10. Henkel Anand India Limited
Location: Kurkumbh, Maharashtra
Plant : Adhesive Plant
Year of Execution : 2018 & 2020
Particulars of Work : Instrumentation Installation Work with supply of Erection Hardware
11. RajashreePolyfil Ltd.
Location : Bharuch
Plant : Polymers
Year of Execution : 2006
Particulars of Work : Instrumentation,Erection and Calibration works with Supply of Material.


1. Torrent Pharma Ltd
Location : Dahej
Plant : API & Formulation (OSD) Facility
Year of Execution : 2013
Particulars of Work : Plantstruxure Distributed Control System; Instrumentation and Erection, Installation & Calibration works with supply of material.
Location : Indrad
Plant : Module F
Year of Execution : 2012
Particulars of Work : Plantstruxure Distributed control system & VFD Communication with Control system, Instrumentation and Erection, Installation & Calibration works with supply of material.
Plant : Module D & E
Year of Execution : 2010
Particulars of Work : Plantstruxure Distributed Control System; Instrumentation and Erection,Installation& Calibration works with supply of material.
2. Avestha Pharma Pvt. Ltd
Location : Wada, Maharastra
Plant : EO Plant
Year of Execution : 2011
Particulars of Work : Plantstruxure Distributed control system, SUPERBatch& Historian for Batch Process Management, Complete Field Instrument supply Installation & Calibration.
3. Dr. Reddy’s Laboratories Ltd
Location : Vishakapatnam, Andhra Pradesh
Plant : FTO-7 Plant � Utility Management System
Year of Execution : 2017
Particulars of Work : APROL DCS system with Supply, Installation, Erection and Commissioning for Instrumentation. Turnkey Instrumentation Work.
Location : Andhra Pradesh
Plant : CTO-6 Plant
Year of Execution : 2014
Particulars of Work : Instrumentation and Erection,Installation& Calibration works with supply of material.
Plant : API Plant
Year of Execution : 2013
Particulars of Work : Instrumentation and Erection,Installation& Calibration works with supply of material.
4. Piramal Healthcare Ltd
Location : Medak
Plant : ATP Plant
Year of Execution : 2014
Particulars of Work : PLC/SCADA based system, Instrumentation, Installation & Calibration work with supply of material. Location : Digwal
Plant : ETP Plant
Year of Execution : 2013
Particulars of Work : Instrumentation and Erection,Installation& Calibration works with supply of material.
5. S. D. Fine-Chem Ltd
Location : Tarapur
Plant : Drug Intermediates
Year of Execution : 2006
Particulars of Work : PLC/SCADA based System for Automation of 8 Nos Speciality Chemical Reactors,Dataacquisition,Control,RecipeManagement,MIS Reports.
5. Cipla Limited
Location : Vikhroli,Mumbai
Plant : Energy Monitoring
Year of Execution : 2011
Particulars of Work : Energy Monitoring System.
6. Mylan Laboratories Ltd.
Location : Taloja, Maharashtra
Plant : API Plant Expansion
Year of Execution : 2016
Particulars of Work : PLC/SCADA Based Control System
7. Ranbaxy Laboratories Ltd
Location : Dewas
Plant : API Plant
Year of Execution : 2005
Particulars of Work : Calibration, Installation & Commissioning of Instruments with supply of erection material.
8. Wockhardt Ltd
Location : Bharuch,Gujarat
Plant : API Plant
Year of Execution : 2007
Particulars of Work : Instrumentation and Erection,Installation& Calibration works with supply of material.
9. Watson Pharma Pvt Ltd
Location : Ambernath
Plant : API Plant
Year of Execution : 2013
Particulars of Work : Intelligent MCC Instrumentation and Erection,Installation& Calibration works with supply of material.
10. Reliance Life Sciences
Location : Navi Mumbai
Plant : Biotech API Plant
Year of Execution : 2007
Particulars of Work : Instrumentation work with supply of material.
11. Sandoz Pvt Ltd
Location : Mahad
Plant : API Plant
Year of Execution : 2007
Particulars of Work : Instrumentation work with supply of material.
12. Megafine Pharma Pvt Ltd
Location : Dindori-Nashik
Plant : API Plant Automation
Year of Execution : 2007
Particulars of Work : Turnkey Instrumentation work for Bulk Drug Plant.


1. Mondelez India Foods Private Limited (Cadbury India)
Location : Rewari
Plant : Bournvita Plant
Year of Execution : 2015
Particulars of Work : Supply Installation and Commissioning of MCC Panel
Location : Baddi, Himachal Pradesh
Plant : Big Band Project of Bournvita
Year of Execution : 2013
Particulars of Work : Plantstruxure Distributed control system, with MCC Panels
2. International Flavours and Fragrances Limited
Location: Sri City, A.P.
Plant: Flavours and Fragrances Plant
Year of execution: 2020
Particulars of Work: Turnkey Automation with Plantstruxure PES Distributed Control System with Complete Field Instrument supply, Installation & Calibration.
3. ***** Yeast India Pvt. Ltd.
Location: Maharashtra
Plant: Yeast Plant
Year of execution: 2020
Particulars of Work: Plantstruxure PES Distributed Control System
Location: UP
Plant: Yeast Plant
Year of execution: 2020
Particulars of Work: Plantstruxure PES Distributed Control System
4. IDMC Limited
Location: Moradabad
Plant: PCDF
Year of execution: 2017
Particulars of Work: Integrated Intelligent MCC Panels
Location: Kanpur
Plant: PCDF
Year of execution: 2017
Particulars of Work: Integrated Intelligent MCC Panels
Location: Varanasi
Plant: PCDF
Year of execution: 2018
Particulars of Work: Integrated Intelligent MCC Panels
Location: Kannuj
Plant: PCDF
Year of execution: 2018
Particulars of Work: Integrated Intelligent MCC Panels
5. Banas Dairy
Location: Palanpur
Plant: Dairy
Year of execution: 2015
Particulars of Work: Control System software development and commissioning
6. First Blends Limited
Location: Lagos, Nigeria
Plant: Flour Based Products
Year of execution: 2016
Particulars of Work: Turnkey Automation with Control System with Complete Field Instrument supply & Commissioning.
7. Zaika Foods
Location: Lagos, Nigeria
Plant: Flour Based Products
Year of execution: 2017
Particulars of Work: Turnkey Automation with Control System with Complete Field Instrument supply & Commissioning.
8.RSPL Limited
Location: Dwarka � Gujarat
Plant: Detergent Plant
Year of execution: 2019
Particulars of Work: Instrumentation Installation Work with supply of Erection Hardware
9. Camphor & Allied Products Limited
Location: Nandesari, Gujarat
Year of execution: 2017
Particulars of Work: Instrumentation Installation Work with supply of Erection Hardware
10. Colgate India Ltd
Location : Sanand,Gujarat
Plant : Toothpaste Plant
Year of Execution : 2013
Particulars of Work : Instrumentation and Erection Installation & Calibration works with supply of material.
11. GlaxoSmithkline Consumer Healthcare India Ltd
Location : Sonepat, Haryana
Plant : Horlicks Plant
Year of Execution : 2012
Particulars of Work : Instrumentation Installation & Calibration work with supply of material.


1. Indian Oil Blending Ltd
Location : Trombay, Mumbai
Plant : Lube Oil Blending Plant
Year of Execution : 2004
Particulars of Work : Turnkey Automation for blending units Data Acquisition,Control,RecipeManagement,MIS Reports.
Location : Taloja
Plant : Lube Oil Blending Plant
Year of Execution : 2017
Particulars of Work : Automation for blending units Data Acquisition, Control,Recipe Management, MIS Reports.
2. Tide Water Oil Co. Ltd (Veedol Lubricants)
Location : Oragadam, Chennai
Plant : Lube Oil Blending
Year of Execution : 2009 – 15
Shifting, PLC/SCADA Based system for Automation of Lube Oil Blending, SUPERBatch for Batch Process Management,Instrument Installation & Calibration work with supply of material.
Location : Turbhe, Navi Mumbai
Plant : Lube Oil Blending
Year of Execution : 2009 – 19
Shifting, PLC/SCADA Based system for Automation of Lube Oil Blending, SUPERBatch for Batch Process Management,Instrument Installation & Calibration work with supply of material.
3. Fuchs Lubricant Ltd
Location : Ambernath, Maharashtra
Plant : Lube Oil Blending Plant
Year of Execution : 2010
Particulars of Work : PLC/SCADA Based system for Automation of Lube Oil Blending, SUPERBatch for Batch Process Management, Instrument Installation & Calibration work with supply of material.
4. Lubrizol India Ltd
Location : Turbhe
Plant : MCC
Year of Execution : 2011
Particulars of Work : Energy Monitoring System and Intelligent MCC communication with DCS.
Plant : Lub Oil Blending Plant
Year of Execution : 2001
Particulars of Work : Design, Detailed Engg for Electrical and Instrumentation..
5. Castrol India Ltd
Location : Patalganga,Maharastra
Plant : Pit Blending
Year of Execution : 2010
Particulars of Work : Supply of Control System.


1. Syngenta India Ltd
Location : goa
Plant : Agni-2
Year of Execution : 2014
Particulars of Work : Instrumentation Installation & Calibration work with supply of material.
Plant : Agrochemicals
Year of Execution : 2012
Particulars of Work : Instrumentation Installation & Calibration work with supply of material.
2. Dow Corning (I) Pvt. Ltd
Location : Ranjangaon,Maharashtra
Plant : Agrochemicals
Year of Execution : 2006
Particulars of Work : Calibration, Installation & Commissioning of Instruments with Supply of Part Erection Material
3. Atul Ltd
Location : Valsad,Gujarat
Plant : JAIN Project
Year of Execution : 2003
Particulars of Work : Instrumentation erection work.
4. Sabero Organics Ltd
Location : Bulsar,Gujarat
Plant : NAHTCP Plant
Year of Execution : 2010
Particulars of Work : PLC based SCADA System.
Location : Sarigam,,Gujarat
Plant : Agrochemicals
Year of Execution : 2002
Particulars of Work : PLC/ SCADA Based System for Automation of Pesticide Manufacturing Batch and Continuous Process
5. Rashtriya Chemicals & Fertilizers Ltd
Location : Chembur, Maharashtra
Plant : Agrochemicals
Year of Execution : 1998
Particulars of Work : Installation, Calibration, Commissioning of Instruments
6. Novartis India Ltd
Location : Goa
Plant : Agrochemicals
Year of Execution : 1998
Particulars of Work : Erection, Calibration, Commissioning of Instruments for Agrochemical Plant alongwith Supply of Material.
7. Bayer India Ltd
Location : Thane, Maharashtra
Plant : Health Care Formulation
Year of Execution : 2000
Particulars of Work : PLC/ SCADA Based System for Data Acquisition and Control of HVAC System for the Formulation Plant.Installation& Commissioning Of Field Instrumentation.
Plant : HVAC System
Year of Execution : 1999
Particulars of Work : Erection, Calibration, Commissioning of Instruments alongwith Supply of material.
Plant : Agrochemicals
Year of Execution : 1997
Particulars of Work : Erection, Calibration, Commissioning of Instruments alongwith Supply of material


1. Indian Oil Corporation Limited (IOCL)
Location : Balasore
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 Control System.
Location : Indore
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 Control System.
Location : Jarsuguda
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 and Process Control System.
Location : Digboi
Project : Terminal Automation System
Year of Execution : 2015
Particulars of Work : Supply of SIL 3 and Process Control System.
Location : Panipat
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 Control System.
Location : Allahabad
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 Control System.
Location : Kanpur
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 Control System.
Location : Betkuchi
Project : Terminal Automation System
Year of Execution : 2015
Particulars of Work : Supply of SIL 3 Control System.
Location : Coimbature
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of Process Control System.
Location : Trichy
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of Process Control System.
Location : Narimanam
Project : Terminal Automation System
Year of Execution : 2015
Particulars of Work : Supply of Process Control System.
Location : Lumbding
Project : Terminal Automation System
Year of Execution : 2015
Particulars of Work : Supply of SIL 3 Control System.
Location : Betkuchi
Project : Terminal Automation System
Year of Execution : 2015
Particulars of Work : Supply of SIL 3 Control System.
2. Bharat Petroleum Corporation Limited (BPCL)
Location : Manmad
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 Control System.
Location : Koyali
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 Control System.
Location : Kandla
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 Control System.
Location : Manglia
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 Control System.
Location : Haldia
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 Control System.
Location : Paradeep
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 Control System.
Location : Patna
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 Control System.
Location : Rajbandh
Project : Terminal Automation System
Year of Execution : 2014
Particulars of Work : Supply of SIL 3 Control System.
Location : Irrumpanam
Project : Terminal Automation System
Year of Execution : 2015
Particulars of Work : Supply of SIL 3 Control System.
3. Reliance Industries Limited
Location :DahejNagothane Ethane Pipeline
Project : Terminal Automation System
Year of Execution : 2015
Particulars of Work : 4 nos. Supply of SIL 3 Control System.


1. Karnataka Power Corporation Limited – Voltas
Location :Bellary
Project : 90MLD WTPPlant
Year of Execution : 2016
Particulars of Work : Supply of Process Control System.
2. UP Jal Nigam – Voltas
Location :Agra
Project : 224MLD & 144MLD WTP Plant
Year of Execution : 2019
Particulars of Work : Supply of Process Control System.
3. Harcros / Esteem Industries
Location :Wada
Project : ETP Plant
Year of Execution : 2018
Particulars of Work : Turnkey Automation with Control System, Complete Field Instrument supply Installation & Calibration.
Location :Goa
Project : ETP Plant
Year of Execution : 2018
Particulars of Work: Turnkey Automation with Control System, Complete Field Instrument supply Installation & Calibration.


1. BKT Tires Limited
Location :Bhuj
Project : Utility Automation
Execution : 2009 to 2017
Particulars of Work: Turnkey Automation with Control System, Complete Field Instrument supply Installation & Calibration.
2. CEAT Tyres
Location :Taloja
Project : EMS
Execution : 2019
Particulars of Work: Energy Management System


1. Asahi India Glass Ltd.
Location: Taloja
Project: Energy Management System on IIoT Platform
Year of execution: 2019
Particulars of Work: Energy Management System on LoRa Network of TATA Communication
2.Hindustan Zinc Ltd.
Location: Bhilwara
Project: Energy Management System on IIoT Platform
Year of execution: 2019
Particulars of Work: Energy Management System on LoRa Network of TATA Communication


1. Birla Cellulose
Location: Kharach
Year of execution: 2019
Particulars of Work: Instrumentation Installation Work with supply of Erection Hardware
2. Bombay Dyeing & Mfg Co. Ltd
Location : Patalganga
Plant : polyester
Year of Execution : 2007
Particulars of Work : Instrumentation work with supply of material for Polyester Plant
3. Garden Silk Mills Ltd
Location : Surat
Plant : polyester
Year of Execution : 2005
Particulars of Work : Calibration, Installation & Commissioning of Instruments
4. IndoRama Synthetics (I) Ltd
Location : Nagpur
Plant : polyester
Year of Execution : 2007
Particulars of Work : Instrumentation work with Supply of Material
Plant : polyester
Year of Execution : 2007
Particulars of Work : PLC Communication with DCS System & SCADA Development for Spinning & Draw Line.
Plant : polyester
Year of Execution : 2002
Particulars of Work : Installation, Calibration of Instruments with Supply of Material
5. Wartsila India Ltd
Location : Kopilvatti,Tamilnadu
Plant : Textile
Year of Execution : 2002
Particulars of Work : PLC/SCADA Based System for Data Acquisition and Control of 6 MW Generator Set.


1. Reliance Communication Limited
Location : Approx. 500 Locations in India
Plant : Utlilty Management for Towers
Year of Execution : 2004 to 2008
Particulars of Work : PLC/SCADA Based system with approx. 500 PLC’s connected on Fiber throughout India.
2. CRI Pumps Ltd
Location : Coimbatore,Tamilnadu
Plant : Pump Test Bed Plant
Year of Execution : 2013
Particulars of Work : PLC/SCADA Based system, Installation & Calibration work with supply of material
3. Wartsila India Ltd.
Location : Kovilpatti, Tamil Nadu
Plant : Textile
Year of Execution : 2002
Particulars of Work : PLC/ SCADA Based System for Data Acquisition and Control of 6 MW Generator Set.
Location : Ariyalur Tamil Nadu
Plant : Cement
Year of Execution : 1999
Particulars of Work : PLC Based System for Data Acquisition and Control of 2 Nos. 6 MW Generator Sets.
Location : Udaipur, Rajasthan
Plant : Textile
Year of Execution : 2001
Particulars of Work : PLC Based System for Data Acquisition and Control of 6 MW Generator Set.
Location : Banswara, Rajasthan
Plant : Textile
Year of Execution : 2002
Particulars of Work : PLC Based System for Data Acquisition and Control of 6 MW Generator Set.
Location : Dandeli, Karnataka
Plant : Paper
Year of Execution : 1999
Particulars of Work : PLC Based System for Data Acquisition and Control of 2 Nos 6 MW Generator Sets
4. Tata Engineering & Locomotive Co. Ltd
Location : Pune
Plant : Indica Car Project
Year of Execution : 1998
Particulars of Work : Erection, Installation & Commissioning – Electrical and Instrumentation